DATE

July 2016 – May 2017

REFERENCE

John Stacpoole

Cairn Hill – South Australia

Mine Surveyor for the start up of an Iron Ore, Gold and Copper Mine south of Coober Pedy in South Australia. Verify existing Horizontal and Vertical Control. Verify and amalgamate existing data to provide a starting Wireframe/DTM of the complete site. Open Pit, Waste Dump, ROM and Rail Siding Surveying and Volume Calculations for Interim and End of Month Claims. Assist with Drill and Blast Design. Design of Site ROM and Skyway from specifications provided by the Mine Manager. Open Pit Setout and Pickup of Crests and Toe Lines, Drill Patterns and As-Drilled. T.B.M. provision to maintain elevations within tolerances. Prism Monitoring for Wall Deformation. Update and Maintain Data including complete site Wireframes/DTMs provided at Interim and End of Month.